Member of GOLDSCHMIDT Thermit Group

Acceptance tests of the SHS heating system for switches

On April 14, 2017, acceptance tests of the SHS heating system of switch points installed in the Murmansk track distance on the station were successfully carried out. Loparskaya Oktyabrskaya railway station. Based on the test results, the acceptance commission recommended the release of the installation series in an amount not less than 10 sets, and assign the O1 letter to the working CD and TD.